Construction contract negotiation comes down to four questions. What is the work, what does it cost, when does it have to be finished, and who carries the risk when something goes wrong. Every clause in the document serves one of those four, and the provisions that cause trouble later are the ones that answer a question vaguely or not at all.

I have practiced for more than 35 years and spent nearly half of that career inside companies, as a corporate officer and in-house counsel. I have sat in the chair where a legal review competes with a start date and a sales target, and where everyone in the room wants the lawyer to be quick. So I am not going to tell you to mark up every page. I am going to tell you which parts repay the time.

What does construction contract negotiation actually cover?

Scope comes first, and it is where most money is lost. The documents that define the work should be identified by name, date and revision, with an order of precedence if they conflict. Exclusions belong in writing, stated affirmatively, because a scope defined only by what is included leaves every gap to argument. On a design-build job, say plainly who owns the design and who owns the means and methods.

Price structure is the second question. A stipulated sum, cost plus a fee, cost plus with a guaranteed maximum, and unit pricing allocate risk very differently, and the right choice depends on how well the work is defined on the day you sign. If the drawings are not finished, a fixed price is a guess and somebody is going to pay for it. Allowances need a stated basis and a mechanism for what happens when the real number lands above it. Material escalation belongs in the contract, not in the first invoice that surprises someone.

Then schedule. Define substantial completion, and define it the way you will actually use it. Say what delay is excusable, how weather is treated, and whether the remedy for late completion is liquidated damages, actual damages or nothing. If there are liquidated damages, they need a daily rate tied to a real estimate of loss, and a cap, because an open-ended daily exposure on a modest contract can consume the entire profit on the job.

Which clauses create the most trouble after the work starts?

Change orders, almost always. The written authorization requirement is in every form and gets ignored in the field, where a superintendent is told to do something and does it. Decide now who has authority to direct a change, how changed work gets priced, whether work proceeds while price is resolved, and how fast a response is required. A change clause nobody can follow under field conditions is worse than a demanding one everybody follows.

Notice provisions sit right behind them. Many contracts condition any claim for extra time or money on written notice inside a short window, and courts in some states enforce that strictly. Whoever administers the contract needs to know those windows on day one. Payment terms belong in the same group. Pay-if-paid and pay-when-paid clauses are not the same thing, and whether the first is enforceable at all varies by state. Retainage, the conditions for its release, and whether lien waivers are conditional or unconditional all deserve a direct look rather than a signature.

After that come the risk-shifting clauses. Indemnity, which may not be enforceable as written in your state. Insurance requirements, additional insured status, waiver of subrogation, and who buys builder’s risk. A consequential damages waiver, which can matter more than any other single provision when the project supports a business operation. Warranty length, what it actually covers, and who honors it when the subcontractor who did the work is gone. Differing or concealed site conditions, which on renovation work is the most likely source of a dispute on the entire job. Termination for convenience, and what the contractor gets paid when it happens.

How much can you really change a standard form contract?

More than people assume, and the real document is often not the form. Construction contract negotiation on an industry standard form usually happens somewhere else entirely, in the supplementary conditions. That is a separate document that rewrites the form’s allocation of risk clause by clause. Read it first. It holds the insurance limits, the notice periods, the indemnity language and the dispute provisions.

Two things constrain the negotiation honestly. On a lender-financed project the loan documents drive terms the parties cannot trade away, including the draw schedule, inspection requirements and consent rights. And subcontract flow-down means a subcontractor inherits obligations from a prime contract it may never have read. If you are signing a subcontract, ask for the prime contract, because you are agreeing to it either way.

So pick your battles. On most jobs three or four provisions carry the actual risk of that project, and a markup treating every clause as equally important earns you a reputation rather than a better contract. Decide what would hurt you most on this job and spend your negotiation there.

What should an owner insist on, and what should a contractor?

If you are the owner, insist on a scope you can hold someone to, a schedule with a defined completion standard and a consequence, payment tied to verified progress rather than to the calendar, retainage with clear release conditions, lien waivers with every payment, certificates of insurance before anyone mobilizes, and a named party who honors the warranty. Put the closeout documents in the contract instead of chasing them later.

If you are the contractor, insist on a change order procedure that works in the field, payment timing with a real remedy for nonpayment including the right to suspend work, notice periods long enough to be met by people who are building something, scope exclusions in writing, no responsibility for design you did not produce, and limits on liquidated and consequential damages. Insist also on knowing who on the owner’s side can actually make a decision.

Both sides benefit from the same two things, which makes them the easiest part of a construction contract negotiation to agree on. One is a short, clear communication and documentation requirement, so the project has a record while it is being built rather than reconstructed afterward. The other is a defined escalation path for disagreements that keeps the work moving while people argue.

How should the contract handle disputes?

Decide deliberately, then make the clause consistent everywhere. A mediation requirement before anything else is usually worth having, because it is cheap and it works more often than people expect. Then choose between arbitration and court with your eyes open. Arbitration is usually faster and private, with limited discovery and almost no appeal. Court gives full discovery, a public record and an appeal, and takes longer.

Two details get overlooked. The first is joinder. Construction disputes rarely involve only two parties, and a clause that cannot bring in the subcontractor, the supplier or the design professional leaves you litigating the same facts twice. The second is consistency. If the prime contract requires arbitration and the subcontracts are silent, you have built a structure where the parties who caused the problem are not in the room. Choose the forum, the governing law and the fee-shifting rule once, and flow them down.

Frequently asked questions

Is a signed proposal a binding contract?

Frequently it is, and that is the problem. The terms become whatever the proposal says plus whatever the law supplies, which is rarely what either party had in mind. If a one-page proposal is all the job justifies, make sure it states scope, exclusions, price basis, schedule, payment timing and how changes get priced.

Do I need a lawyer on a small job?

Not always, and the right measure is proportion. The jobs worth a review are the ones where the price is large relative to the business, where a delay has consequences beyond the project, where a lender or a public owner is involved, or where you are handed a long document you did not write. A short review before signing costs a fraction of a dispute about the same clause.

Can we use a standard industry form and leave it alone?

You can, and it beats having no written contract at all. Understand that the forms assume a particular delivery structure and a particular balance of risk, and that the supplementary conditions attached to them often change that balance substantially. In any construction contract negotiation, read what is attached to the form with more care than you read the form.

Talk with Sheldon

A good part of my construction work is on the front end, negotiating agreements before anyone breaks ground, and the rest is resolving disputes a better agreement would have prevented. I will tell you which provisions on your job carry real risk and which are fine as written, and I will do it on a schedule that does not hold up your start date. If you have a contract in front of you, send it over. Reach me at skorlin@aegislaw.com.

By Sheldon Korlin, Attorney, AEGIS Law

Attorney Advertising. This article is general information published by AEGIS Law for marketing purposes. It is not legal advice and should not be relied on as legal advice. It may not reflect current law, may not apply in your state or to your facts, and may contain errors or omissions. Laws change often and vary from state to state. Before acting on anything you read here, talk with a lawyer licensed in your jurisdiction who has reviewed your situation. Reading this article or contacting AEGIS Law does not create an attorney-client relationship, and you should not send confidential information until one exists. AEGIS Law lawyers are licensed in various states, and no lawyer is licensed in every state. Unless stated otherwise, no AEGIS Law lawyer is certified as a specialist by any state board or certifying organization. Prior results do not guarantee a similar outcome. Lawyer responsible for this content: Scott Levine, AEGIS Law, 601 S. Lindbergh Blvd., Frontenac, Missouri 63131, (314) 454-9100. The choice of a lawyer is an important decision and should not be based solely upon advertisements.

Select Categories

Strategic Engagement

Consult with our Managing Partner.

Ready to review your enterprise risk or legacy strategy? Schedule a direct consultation with Scott Levine using the link below.

Schedule an Appointment

BOOK NOW


Call Us

(314) 454-9100