Mechanics lien rights are won or lost on deadlines, and the deadlines start running from the work, not from the nonpayment. By the time an owner or general contractor stops returning calls, a contractor who did not paper the job correctly may already be out of time. The inverse is also true, and it is the point of this article: a contractor who runs clean paperwork from the first day rarely needs the lawsuit, because a properly preserved lien changes the conversation about payment all by itself.
I represent contractors, builders, and trade companies across Colorado in lien and payment disputes, including lien foreclosures, and the cases follow a pattern. The contractors who collect are not the ones with the best lawyers. They are the ones whose job files made the lien easy to perfect and hard to attack. Lien law is a creature of statute and every state’s rules differ; what follows describes Colorado’s general mechanics lien statute, Article 22 of Title 38 of the Colorado Revised Statutes, and if you build in another state, the structure is similar but the deadlines are not.
Who has lien rights, and for what?
Colorado’s statute is broad. General contractors, subcontractors, laborers, material suppliers, equipment lessors, and design professionals such as architects and engineers can all claim lien rights for the value of labor, materials, or services that went into improving real property. The lien attaches to the property itself, which is the whole point: it converts an unpaid invoice into an interest in the land the work improved, and it puts the owner’s title, financing, and sale plans in play until the debt is addressed.
Two boundaries matter. First, the work must actually improve the property. Second, public projects are different: you generally cannot lien government property, and on public work the remedy is a claim against the payment bond the statute requires, with its own notice rules and its own deadlines. A contractor who moves between private and public work needs both playbooks, because filing the private-work paperwork on a public job protects nothing.
Lien rights also do not depend on having a contract with the owner. A subcontractor two tiers down from the owner can lien the project for unpaid work. That is exactly why owners and general contractors manage lien exposure so actively, and why the waiver documents discussed below get so much attention.
What are the deadlines?
Colorado’s structure has three steps, and each has a clock. First, before recording, a lien claimant must serve the owner and the principal contractor with a notice of intent to file a lien at least ten days before the lien statement is recorded. The notice of intent is not a hostile act. It is a statutory prerequisite, and in practice it is also the single most effective collection letter in construction, because it arrives with consequences attached.
Second, the lien statement itself must be recorded with the clerk and recorder of the county where the property sits, within the statutory window measured from completion of work. For most claimants in Colorado that window is four months after the last labor or materials were furnished, with a shorter two month period for claimants who supplied only labor. What counts as the last work is a litigated question, and returning to the job for a trivial punch item does not reliably restart the clock, so the safe practice is to calendar from the last substantial work.
Third, a recorded lien does not last forever. In Colorado, the claimant must commence a foreclosure action within six months after completion of the project or the lien expires, though a recorded lien can be extended in limited circumstances. Every one of these numbers varies by state, and several change with the facts of the job, so treat the calendar as a legal question, not an office task. The discipline is simple: on every job, the day work starts, someone should know the dates by which a notice of intent, a lien statement, and a foreclosure complaint would each have to go out.
How does a lien turn into money?
A perfected lien creates leverage in three ways. Priority is the first: a mechanics lien in Colorado relates back to the commencement of work on the project, which can place it ahead of interests recorded after the work began. Positioned that way, the lien is a cloud the owner’s lender and any buyer must deal with, which is why perfected liens so often produce payment without trial.
Foreclosure is the second. The lien is enforced through a court action that can ultimately order the property sold to satisfy the debt. In practice, most foreclosure actions settle once the lien survives the owner’s initial attacks, and those attacks are predictable: the lien was late, the notice of intent was defective, the amounts include unliened items, or the work was defective and the sums are disputed. Every one of those defenses is answered in advance by the job file, which is the quiet theme of this entire article.
The third form of leverage cuts the other way, and contractors must respect it. Colorado penalizes excessive liens: a claimant who records a lien for an amount greater than is due, knowingly, can forfeit the lien entirely and become liable for the owner’s costs and attorney fees. Lien for what the records support, exclude disputed extras you cannot document, and resist the temptation to use the lien amount as a negotiating ask. The statute is a payment remedy, not a pressure valve.
What should your contracts and paperwork do?
Start with the contract, because lien rights protect the amounts the contract supports. A clear scope, a schedule of values, progress billing tied to measurable milestones, and a written change order requirement are what make a lien amount provable. The change order discipline matters doubly, since unapproved extras are both the most commonly unpaid amounts and the hardest to lien defensibly. If you work as a subcontractor, the terms that flow down from above deserve real review, a point I made in an article on why the customer’s contract is not your contract, and if you hire subs yourself, a proper written subcontract agreement protects the same interests from the other side.
Then run the job file as if a judge will read it. Daily logs or photographs tying labor and deliveries to dates, delivery tickets, signed change orders, and billing records that match the schedule of values. The two dates that control the lien calendar, first work and last work, should be provable from your own records rather than reconstructed from memory.
Finally, manage lien waivers deliberately, because they are where contractors give lien rights away by accident. A conditional waiver releases rights only when the payment actually clears; an unconditional waiver releases them the moment it is signed, paid or not. Never sign an unconditional waiver for money you have not received, read whether the waiver covers just the progress payment or everything through a date, and train whoever signs paperwork at your company on the difference. Owners and lenders process waivers on autopilot. You cannot afford to.
Frequently asked questions
Can I lien for unapproved change orders?
Risky. The lien should reflect amounts you can prove are due, and extras performed without the written approval your contract requires are the softest part of any claim. Document the direction you received and the value added, assert the amounts you can support, and remember that Colorado’s excessive lien penalty punishes knowing overstatement. The better answer is upstream: stop work until the change order is signed.
What if the owner already paid the general contractor?
In Colorado, an owner’s payment to the general contractor does not automatically extinguish a subcontractor’s lien rights, which is precisely why owners demand waivers from subs and suppliers before releasing funds. There are limits and defenses, including statutory protections in some residential situations, so get advice on the specific job. From the sub’s side, the lesson is to perfect your rights rather than assume payment upstream protects you.
Does a lien expire?
Yes. A Colorado mechanics lien generally must be foreclosed within six months after completion of the project, and a lien left to expire is as if it never existed. Record, then calendar the foreclosure deadline the same day. A lien that is about to lapse has also lost most of its negotiating force, so the time to use the leverage is early.
Talk with Rod
Payment problems on construction projects reward the contractor who prepared before the dispute started, and the preparation is mostly paperwork you control. If you want your contracts, notices, and lien practices built so the next slow payer is a process rather than a crisis, I can help. I practice tax, estate planning, and business law at AEGIS Law, representing Colorado contractors and builders from Denver. Reach me at ratherton@aegislaw.com.
By Rod Atherton, Tax, Estate Planning and Business Attorney, AEGIS Law